Orders
CommittedKampala National Medical Stores
10024834 · SAP SD · Uganda · A. Iyer · Export SalesPithampur, Madhya Pradesh
Why late · +6 d
Materials ready 25 Oct → LF-1 reserved for domestic MTS until 16 Nov → MLT 4 d → ships 27 Nov → arrives 20 Dec; committed 14 Dec → +6 d
1 · Verdict
Can deliver in 60 days
60 d✓
90 d✓
120 d✓
Earliest delivery: P50 20 Dec 2026/P90 14 Dec 2026
Firmed against the manufacturing and QC schedule.
2 · Floor now
Code · name / status / now / next / load 60 d / free from
LF-1 · Liquid filling & capping line
Idle
Now —
Next B26-1057 · Sat 31 Oct 16:00
95%
Free 17 Nov 2026
3 · Impact
Order already committed. Its firm schedule is shown below.
4 · Schedule
90,000 bottles → 3 batches · Recipe batch size 30,000 · Manufacturing routing → QC tests → QA release
ResourceLoad 60 d
Today
Sun
26 Oct
Sun
2 Nov
Sun
9 Nov
Sun
16 Nov
Sun
23 Nov
Sun
30 Nov
Sun
7 Dec
Sun
14 Dec
Sun
21 Dec
Sun
28 Dec
Sun
4 Jan
Sun
11 Jan
Sun
18 Jan
Sun
25 Jan
Sun
1 Feb
Sun
8 Feb
Sun
15 Feb
Liquid filling &…95%
Liquid dispensing48%
Manufacturing ves…57%
Bottle labelling53%
Bottle cartoning51%
+6d
HPLC 561%
Analyst 552%
QA reviewer16%
HPLC 265%
Analyst 254%
Analyst 757%
Analyst 465%
| Dispensing | Thu 22 Oct 07:00 IST | Thu 22 Oct 10:00 IST | ||
| Manufacturing | MV-1 | Thu 22 Oct 10:00 IST | Thu 22 Oct 18:00 IST | |
| Liquid filling & capping | LF-1 | Sat 31 Oct 16:00 IST | Sun 1 Nov 08:00 IST | |
| Labelling | LBL-1 | Sun 1 Nov 08:00 IST | Sun 1 Nov 14:00 IST | |
| Cartoning | LC-1 | Sun 1 Nov 14:00 IST | Sun 1 Nov 18:00 IST | |
| Assay | Sun 1 Nov 18:00 IST | Sun 1 Nov 21:00 IST | ||
| pH | Sun 1 Nov 19:00 IST | Sun 1 Nov 21:00 IST | ||
| Microbial limits | Sun 1 Nov 21:00 IST | Sun 1 Nov 22:00 IST | ||
| Batch record review | Fri 6 Nov 22:00 IST | Sat 7 Nov 02:00 IST | ||
| Dispensing | Fri 23 Oct 16:00 IST | Fri 23 Oct 19:00 IST | ||
| Manufacturing | MV-1 | Mon 26 Oct 01:00 IST | Mon 26 Oct 13:00 IST | |
| Liquid filling & capping | LF-1 | Sun 1 Nov 08:00 IST | Sun 1 Nov 20:00 IST | |
| Labelling | LBL-1 | Sun 1 Nov 20:00 IST | Mon 2 Nov 02:00 IST | |
| Cartoning | LC-1 | Mon 2 Nov 06:00 IST | Mon 2 Nov 10:00 IST | |
| Assay | Mon 2 Nov 10:00 IST | Mon 2 Nov 13:00 IST | ||
| pH | Mon 2 Nov 10:00 IST | Mon 2 Nov 12:00 IST | ||
| Microbial limits | Mon 2 Nov 10:00 IST | Mon 2 Nov 11:00 IST | ||
| Batch record review | Sat 7 Nov 11:00 IST | Sat 7 Nov 15:00 IST | ||
| Dispensing | Mon 26 Oct 00:00 IST | Mon 26 Oct 07:00 IST | ||
| Manufacturing | MV-1 | Mon 26 Oct 13:00 IST | Mon 26 Oct 21:00 IST | |
| Liquid filling & capping | LF-1 | Mon 16 Nov 20:00 IST | Tue 17 Nov 12:00 IST | |
| Labelling | LBL-1 | Tue 17 Nov 12:00 IST | Tue 17 Nov 18:00 IST | |
| Cartoning | LC-1 | Tue 17 Nov 18:00 IST | Tue 17 Nov 22:00 IST | |
| Assay | Tue 17 Nov 22:00 IST | Wed 18 Nov 01:00 IST | ||
| pH | Tue 17 Nov 22:00 IST | Wed 18 Nov 00:00 IST | ||
| Microbial limits | Tue 17 Nov 23:00 IST | Wed 18 Nov 00:00 IST | ||
| Batch record review | Mon 23 Nov 00:00 IST | Mon 23 Nov 08:00 IST |
Bars show the P50 operating schedule; P90 includes the existing QC, release, transit and breakdown allowances.
5 · Commit
Committed · SO 10024834 · Promise 14 Dec 2026
Activity
Imported from SAP SD · committed sales order