Mombasa Health Supplies Ltd
RFQ-2026-0501 · Email · Kenya · A. Iyer · Export SalesDahej SEZ, Gujarat
1 · Verdict
Can deliver in 120 days · not in 90
Earliest delivery: P50 23 Jan 2027/P90 10 Feb 2027
Artemether available 25 Nov 2026; COAT-1 — Sunday · no shift until 21 Dec 2026.
Artemether imported, arrives 25 Nov 2026 · packaging material 28d (Kenya), not in stock
COAT-1 10d · FBD-1 9d · C-1 4d · RMG-1 2d · BP-1 2d · DB-1 1d · +5d breakdown buffer in P90
2 batches of 3,00,000 tablets
Batch record review 4h · release P50 2d / P90 4d
2d pack + transit P50 18d / P90 26d
2 · Floor now
3 · Impact
| 19 Feb 2027 | +30 d | None | 88% current90% with this order | 60 → 60 dIllustrative cover | ||
| 19 Feb 2027 | +30 d | None | 88% current90% with this order | 60 → 60 dIllustrative cover | ||
| 10 Feb 2027 | +21 d | None | 88% current90% with this order | 60 → 58 dIllustrative cover | ||
| 19 Feb 2027First 1 batches: 2 Feb 2027 | +30 d | None | 88% current90% with this order | 60 → 60 dIllustrative cover |
Expedite options
Fastest achievable P90 with selected options · 10 Feb 2027 · 9 d saved
Current · P50 31 Jan 2027 / P90 19 Feb 2027
Materials 34 d · manufacturing & queue 45 d · QC & QA 13 d · transit 26 d
Expedited · P50 23 Jan 2027 / P90 10 Feb 2027
Materials 34 d · manufacturing & queue 36 d · QC & QA 13 d · transit 26 d
No gain for this order
Hold unpacked bulk as pending packaging; unchanged QC and QA · Approver: Planning
No gain for this order
Regulator-approved artwork unchanged · printer 28 → 14 d · ~₹40k expediting · Approver: Purchase
9 d saved (P90) · new P90 10 Feb 2027
Defer domestic replenishment; 30-day stock-cover minimum · cover 60 → 58 d · Approver: Supply Chain head
21 d saved (P90) · new P90 20 Jan 2027
Add to quote, customer pays · transit P50 3 d / P90 5 d · Approver: Customer
82 d earlier first shipment · new P90 10 Feb 2027
Released stock registered for this country and manufacturing site; second freight booking · Approver: Sales / Customer
60,000 tablets · 20 Nov 2026 · Released registered finished stock
5,40,000 tablets · 10 Feb 2027 · Manufacture balance
Production can't move to another site — the product is registered with the importing country's regulator against a specific manufacturing site.
4 · Schedule
6,00,000 tablets → 2 batches · Recipe batch size 3,00,000 · Manufacturing routing → QC tests → QA release
| Dispensing | Wed 25 Nov 17:00 IST | Wed 25 Nov 20:00 IST | ||
| Granulation | Wed 25 Nov 20:00 IST | Thu 26 Nov 08:00 IST | ||
| Fluid bed drying | Mon 7 Dec 15:00 IST | Mon 7 Dec 21:00 IST | ||
| Compression | Fri 11 Dec 16:00 IST | Sat 12 Dec 10:00 IST | ||
| Coating | COAT-1 | Sat 12 Dec 10:00 IST | Sat 12 Dec 22:00 IST | |
| Blister packing | Mon 14 Dec 20:00 IST | Tue 15 Dec 14:00 IST | ||
| Cartoning | Thu 17 Dec 16:00 IST | Thu 17 Dec 22:00 IST | ||
| Assay | Thu 17 Dec 22:00 IST | Fri 18 Dec 01:00 IST | ||
| Dissolution | Fri 18 Dec 01:00 IST | Fri 18 Dec 11:00 IST | ||
| Related substances | Thu 17 Dec 22:00 IST | Fri 18 Dec 02:00 IST | ||
| Microbial limits | Thu 17 Dec 22:00 IST | Thu 17 Dec 23:00 IST | ||
| Batch record review | Tue 22 Dec 23:00 IST | Wed 23 Dec 07:00 IST | ||
| Dispensing | Wed 25 Nov 20:00 IST | Wed 25 Nov 23:00 IST | ||
| Granulation | Sat 28 Nov 09:00 IST | Sat 28 Nov 17:00 IST | ||
| Fluid bed drying | Mon 7 Dec 21:00 IST | Tue 8 Dec 07:00 IST | ||
| Compression | Sat 12 Dec 10:00 IST | Sun 13 Dec 00:00 IST | ||
| Coating | COAT-1 | Wed 23 Dec 06:00 IST | Wed 23 Dec 18:00 IST | |
| Blister packing | Fri 25 Dec 15:00 IST | Sat 26 Dec 09:00 IST | ||
| Cartoning | Sat 26 Dec 09:00 IST | Sat 26 Dec 15:00 IST | ||
| Assay | Sat 26 Dec 15:00 IST | Sat 26 Dec 18:00 IST | ||
| Dissolution | Sat 26 Dec 17:00 IST | Sat 26 Dec 23:00 IST | ||
| Related substances | Sat 26 Dec 18:00 IST | Sat 26 Dec 22:00 IST | ||
| Microbial limits | Sat 26 Dec 15:00 IST | Sat 26 Dec 16:00 IST | ||
| Batch record review | Thu 31 Dec 16:00 IST | Thu 31 Dec 20:00 IST |
Bars show the P50 operating schedule; P90 includes the existing QC, release, transit and breakdown allowances.
5 · Commit
4 existing orders move. Commitment goes to Draft; approvals: Supply Chain head; publish before notifying owners.
Activity
Received · 23 Oct 2026 06:00 IST