Kampala National Medical Stores
RFQ-2026-0503 · Tender call-off · Uganda · M. Rao · Key AccountsDahej SEZ, Gujarat
1 · Verdict
Delivery exceeds 120 days
Earliest delivery: P50 1 Feb 2027/P90 21 Feb 2027
Artemether available 25 Nov 2026; COAT-1 — Sunday · no shift until 21 Dec 2026.
Artemether imported, arrives 25 Nov 2026 · packaging material 28d (Uganda), not in stock
COAT-1 13d · FBD-1 9d · C-1 4d · BP-1 3d · RMG-1 2d · DB-1 1d · +6d breakdown buffer in P90
2 batches of 5,00,000 tablets
Batch record review 4h · release P50 2d / P90 4d
2d pack + transit P50 23d / P90 32d
2 · Floor now
3 · Impact
| 1 Mar 2027 | +29 d | None | 88% current88% with this order | 60 → 60 dIllustrative cover | ||
| 1 Mar 2027 | +29 d | None | 88% current88% with this order | 60 → 60 dIllustrative cover | ||
| 21 Feb 2027 | +21 d | None | 88% current88% with this order | 60 → 58 dIllustrative cover | ||
| 1 Mar 2027First 1 batches: 26 Feb 2027 | +29 d | None | 88% current88% with this order | 60 → 60 dIllustrative cover |
Expedite options
Fastest achievable P90 with selected options · 21 Feb 2027 · 8 d saved
Current · P50 8 Feb 2027 / P90 1 Mar 2027
Materials 34 d · manufacturing & queue 50 d · QC & QA 12 d · transit 32 d
Expedited · P50 1 Feb 2027 / P90 21 Feb 2027
Materials 34 d · manufacturing & queue 41 d · QC & QA 13 d · transit 32 d
No gain for this order
Hold unpacked bulk as pending packaging; unchanged QC and QA · Approver: Planning
No gain for this order
Regulator-approved artwork unchanged · printer 28 → 14 d · ~₹40k expediting · Approver: Purchase
8 d saved (P90) · new P90 21 Feb 2027
Defer domestic replenishment; 30-day stock-cover minimum · cover 60 → 58 d · Approver: Supply Chain head
27 d saved (P90) · new P90 25 Jan 2027
Add to quote, customer pays · transit P50 3 d / P90 5 d · Approver: Customer
87 d earlier first shipment · new P90 21 Feb 2027
Released stock registered for this country and manufacturing site; second freight booking · Approver: Sales / Customer
2,00,000 tablets · 26 Nov 2026 · Released registered finished stock
8,00,000 tablets · 21 Feb 2027 · Manufacture balance
Production can't move to another site — the product is registered with the importing country's regulator against a specific manufacturing site.
4 · Schedule
10,00,000 tablets → 2 batches · Recipe batch size 5,00,000 · Manufacturing routing → QC tests → QA release
| Dispensing | Wed 25 Nov 17:00 IST | Wed 25 Nov 20:00 IST | ||
| Granulation | Wed 25 Nov 20:00 IST | Thu 26 Nov 08:00 IST | ||
| Fluid bed drying | Mon 7 Dec 15:00 IST | Mon 7 Dec 21:00 IST | ||
| Compression | Fri 11 Dec 16:00 IST | Sat 12 Dec 10:00 IST | ||
| Coating | COAT-1 | Wed 23 Dec 06:00 IST | Wed 23 Dec 18:00 IST | |
| Blister packing | Fri 25 Dec 15:00 IST | Sat 26 Dec 09:00 IST | ||
| Cartoning | Sat 26 Dec 09:00 IST | Sat 26 Dec 15:00 IST | ||
| Assay | Sat 26 Dec 15:00 IST | Sat 26 Dec 18:00 IST | ||
| Dissolution | Sat 26 Dec 17:00 IST | Sat 26 Dec 23:00 IST | ||
| Related substances | Sat 26 Dec 18:00 IST | Sat 26 Dec 22:00 IST | ||
| Microbial limits | Sat 26 Dec 15:00 IST | Sat 26 Dec 16:00 IST | ||
| Batch record review | Thu 31 Dec 16:00 IST | Thu 31 Dec 20:00 IST | ||
| Dispensing | Wed 25 Nov 20:00 IST | Wed 25 Nov 23:00 IST | ||
| Granulation | Sat 28 Nov 09:00 IST | Sat 28 Nov 17:00 IST | ||
| Fluid bed drying | Mon 7 Dec 21:00 IST | Tue 8 Dec 07:00 IST | ||
| Compression | Sat 12 Dec 10:00 IST | Sun 13 Dec 00:00 IST | ||
| Coating | COAT-1 | Fri 25 Dec 22:00 IST | Sat 26 Dec 14:00 IST | |
| Blister packing | Tue 29 Dec 06:00 IST | Tue 29 Dec 20:00 IST | ||
| Cartoning | Tue 29 Dec 20:00 IST | Wed 30 Dec 02:00 IST | ||
| Assay | Wed 30 Dec 06:00 IST | Wed 30 Dec 09:00 IST | ||
| Dissolution | Wed 30 Dec 06:00 IST | Wed 30 Dec 12:00 IST | ||
| Related substances | Wed 30 Dec 06:00 IST | Wed 30 Dec 10:00 IST | ||
| Microbial limits | Wed 30 Dec 06:00 IST | Wed 30 Dec 07:00 IST | ||
| Batch record review | Mon 4 Jan 07:00 IST | Mon 4 Jan 11:00 IST |
Bars show the P50 operating schedule; P90 includes the existing QC, release, transit and breakdown allowances.
5 · Commit
4 existing orders move. Commitment goes to Draft; approvals: Supply Chain head; publish before notifying owners.
Activity
Received · 23 Oct 2026 06:00 IST